• 615.661.7979
  • 217 Ward Circle, Brentwood, Tennessee 37027
centene-plaza
  • DESIGN TEAM:
  • Client & Precast Manufacturer Metromont Nashville
  • Architect Forum
  • Contractor Clayco
  • Structural Engineers Uzun & Case
  • Precast Engineers TRC Worldwide Engineering
  • New Construction 504,000 GSF

Centene Plaza Parking Structure - Clayton, Missouri

TRC Worldwide Engineering, Inc. provided precast specialty engineering services for this 8 level, 3 bay parking structure above ground with 2 levels below ground. The structure will have two full height stair towers and one full height elevator tower.

Key Structural Components
  • Double T's, Columns, Beams, Wall Panels
  • LB Spandrels & NLB Spandrels
  • Shear walls & Metro walls

BACK TO PRECAST