  • DESIGN TEAM:
  • Client/ArchitectThe Estopinal Group / HOK
  • ContractorBrasfield & Gorrie, The Lemoine Company
  • Structural Engineers/Steel DetailierTRC Worldwide Engineering
  • New Construction394,000 GSF
  • Construction Cost$211 million

Our Lady of Lourdes Hospital Lafayette, Louisiana

TRCprovided structural engineering services for this new replacement hospital designed to accommodate the addition of a medical office building. TRC is also utilizing Early Steel Detailing to produce structural steel shop drawings for approximately 3,000 tons of steel. Steel detailing will begin at the design development level of the construction document process using the structural RAM model developed by the structural engineer. Steel shop drawings should be released for fabrication approximately one month after the structural steel shell package is released.